Case Study — Solar 2025

Solar + Battery - Benalmádena

12kW solar with 15.4kWh battery for a Benalmádena townhouse community — collective autoconsumo under RD 244/2019 with individual metering and proportional surplus compensation across six units.

Benalmádena, Málaga September 2025Ben HaydenBy Ben Hayden
Benalmádena, Costa del Sol — collective solar and battery for a 6-unit townhouse community. Individual meters per RD 244/2019; surplus proportionally distributed by Endesa.
Benalmádena, Costa del Sol — collective solar and battery for a 6-unit townhouse community. Individual meters per RD 244/2019; surplus proportionally distributed by Endesa.

Project Overview

Location
Benalmádena, Málaga
Property Type
Solar
Service
Solar
Key Issue
Collective Autoconsumo — Individual Benefit Allocation Across 6 Units
Key Result
See the installation scope and equipment below; no financial outcome is promised.
—
Annual Production
—
Energy Savings
—
Annual Savings
—
Payback Period
—
CO₂ Reduction

The Challenge: Collective Autoconsumo — Individual Benefit Allocation Across 6 Units

The Benalmádena coastal apartment complex — 6 privately-owned units sharing a communal garden, pool, and electrical room — had never taken collective action on shared costs despite the building's communal electricity spend reaching €14,000 per year. Individual unit owners were sceptical of community solar arrangements: who owns the equipment, who maintains it, and what happens if an apartment is sold? Our challenge was not just technical — it was facilitating the community agreement, addressing each owner's legal and financial concerns, and designing a system that was demonstrably fair in its allocation of solar benefits.

The Solution

12kW solar with 15kWh battery for coastal apartment complex. Shared system reduces electricity costs for 6 units.

Technical Specifications

  • 24 x 500W Jinko Tiger Neo panels
  • Fronius Symo GEN24 12.0 Plus
  • BYD Battery-Box Premium HVS 15.4kWh
  • Smart energy distribution system
  • Individual metering per apartment

Our Installation Process

1

Community Agreement Facilitation

We prepared a community solar proposal document setting out: ownership structure (community common element), maintenance responsibility, allocation methodology, and the process for energy credit transfer on apartment sale. A community meeting was facilitated where we answered owners' questions. A simple majority vote (4 of 6 owners) approved the project — under the 2019 Royal Decree reforms, community solar improvements require only a simple majority.

2

12kW Solar + 15.4kWh Battery System

24 × 500W Jinko Tiger Neo panels were installed on the flat communal roof in a south-oriented array with 20° tilt. The Fronius Symo GEN24 12.0 Plus hybrid inverter connects to a BYD Battery-Box Premium HVS 15.4kWh battery, storing daytime solar generation for evening use when communal area demand (pool pump, garden lighting, hallway lighting) peaks.

3

Individual Metering & CAU Registration

Individual smart meters were installed at each apartment's supply point, recording both total consumption and allocated solar consumption. The collective CAU was registered under the community's CIF number with Endesa. The solar allocation algorithm distributes generation proportionally to each unit's actual consumption — measured each month and adjusted quarterly if consumption patterns change.

4

Boletín Eléctrico, Battery BMS Test & Community Handover

The full Boletín Eléctrico covering the rooftop solar installation, battery storage system, and new distribution circuits was completed by our REBT-authorised engineer and submitted to the Delegación de Industria within 5 working days of commissioning. The Pylontech battery BMS was commissioned with a discharge depth set to 15% minimum — protecting cell chemistry while still providing 85% usable capacity. A controlled discharge test was conducted with the AC supply to the inverter isolated: the 30kWh battery bank sustained the building's common area loads (stairwell lighting, lift, intercom system) for 9.5 hours — confirming meaningful backup capability for the shared infrastructure. The community president received a full handover pack including CAU certificates, Boletín, battery commissioning data, and login credentials for the SolarEdge monitoring portal — enabling the community administrator to generate monthly energy reports for the owners' assembly.

Results

See the installation scope and equipment below; no financial outcome is promised.

Backed by Research

References for checking the proposed design. These sources do not certify this project's performance, savings, eligibility or commissioning records.

Estimate solar yield for the actual site

Annual generation depends on location, orientation, tilt, shading and system losses. An irradiance figure is not a guaranteed yield per installed kilowatt. State the assumptions and compare the estimate with the property's consumption.

European Commission — PVGIS ↗

Check the applicable self-consumption arrangement

RD 244/2019 regulates administrative, technical and economic conditions for self-consumption. Export compensation is subject to the applicable arrangement and contract; exported energy is not automatically valued at the retail import price.

BOE — RD 244/2019 ↗

Tax relief needs separate eligibility checks

Do not assume solar qualifies for an income-tax deduction or a standard municipal IBI discount. Check current AEAT conditions and the property's municipal ordinance, required evidence, dates and application process before including an incentive in a budget.

Agencia Tributaria — current tax guidance ↗
Residential communities in Benalmadena are where we see the most genuine ROI from solar — Spanish coastal apartment blocks have flat roofs, high community electricity bills (lift, pool pump, lighting), and owners who have watched their community fees rise every year. The collective CAU registration process is more involved than a single house, but once it's done, every apartment sees a direct reduction in their community charge. That's a very tangible outcome that gets talked about at every community meeting.
Craig Whitham
Craig Whitham
Electrical Director, LIT Electricians SL

Frequently Asked Questions

About the Author

Ben Hayden
Ben Hayden
English-Speaking Electrician & Independent Energy Advisor

Ben Hayden is an English speaking electrician and independent energy advisor based in Marbella, Spain, with over 15 years of electrical experience across Europe. He provides independent energy and electrical checks for overseas property owners and managers across the Costa del Sol — helping clients cut electricity bills, navigate Spanish regulations, and make confident decisions on solar PV, heat pump, EV charger and battery storage projects. Ben advises in plain English on projects where the paperwork is in Spanish and the stakes are high. His writing has appeared in ExpatArrivals, The Olive Press, Euro Weekly News, BuildingTalk and pv magazine.